PROPOSED 2018/19 AND FUTURE YEARS’ LTP CAPITAL PROGRAMME ALLOCATIONS
Project/Scheme |
Description (please see Footnotes below for explanation of symbols) |
2018/19 Proposed Allocation (£’000s) |
2019/20 Indicative future allocation (£’000s) |
2020/21 Indicative future allocation (£’000s) |
CAPITAL RENEWAL/MAINTENANCE SCHEMES |
||||
Maintaining links and routes to improve…………. |
||||
Surfaces |
Roads # |
1005 |
tbc |
tbc |
|
Pavement/Footways |
150 |
tbc |
tbc |
Drainage |
Replacement of failed gullies/soakaways |
200 |
tbc |
tbc |
Street Lighting |
Replacement of connections and columns@ |
300 |
300 |
300 |
Bridges & Structures |
A259 King’s Road Arches (Phases 4/5) – preliminary investigation |
100 |
tbc |
tbc |
|
Former West Street Shelter Hall (A259)* |
1500 |
1500 |
0 |
|
Marine Parade retaining wall (Duke’s Mound) |
100 |
tbc |
tbc |
|
Other locations |
15 |
tbc |
tbc |
Highway Asset Management |
Surveys, update inventory and finalise strategy evidence |
75 |
75 |
75 |
CAPITAL RENEWAL/MAINTENANCE SUB-TOTAL |
3,445 |
2,110 |
1,110 |
|
|
||||
INTEGRATED TRANSPORT SCHEMES |
||||
Connecting people with………. |
||||
Education, Training & Learning |
Safer Routes to Schools |
60 |
tbc |
tbc |
|
School Travel Plan Measures*** |
20 |
20 |
0 |
SUB-TOTAL |
80 |
|
|
|
Workplaces & job opportunities |
Business Travel Plan Measures*** |
20 |
20 |
0 |
|
Personalised Travel Planning*** |
20 |
20 |
0 |
SUB-TOTAL |
40 |
|
|
|
Shopping areas |
Boundary Road/Station Road - Portslade |
20 |
tbc |
tbc |
SUB-TOTAL |
20 |
|
|
|
Parks, open spaces & the National Park |
Rights of Way – incl. access to SDNP |
25 |
tbc |
tbc |
SUB-TOTAL |
25 |
|
|
|
Interchanges |
Cycle parking |
40 |
0 |
0 |
|
Motorcycle parking |
10 |
10 |
10 |
|
Accessible bus-stops |
35 |
tbc |
tbc |
SUB-TOTAL |
85 |
|
|
|
Improving neighbourhoods with………. |
||||
Road Safety |
20mph limits – monitoring and speed reduction measures |
80 |
0 |
0 |
|
High risk sites |
100 |
tbc |
tbc |
SUB-TOTAL |
180 |
|
|
|
Air Quality |
Electric vehicle charging points |
55 |
55 |
55 |
|
SUB-TOTAL |
55 |
|
|
Active travel measures |
Pedestrian crossings – freestanding sites |
100 |
tbc |
tbc |
|
Walking network – incl. dropped kerbs and handrails |
50 |
tbc |
tbc |
|
Cycle network*** |
40 |
40 |
tbc |
SUB-TOTAL
continued……/ |
190 |
|
|
|
Managing links and routes with………. |
||||
Technology & Travel Information |
Intelligent Transport Systems [ITS] package - Phase 2 (Wilson Avenue/Roedean Road)~ |
100 |
tbc |
tbc |
|
SUB-TOTAL |
100 |
|
|
Strategic/corridor improvements |
A270 Elm Grove traffic signals |
15 |
0 |
0 |
|
Valley Gardens:Phases 1 & 2** |
892 |
57 |
0 |
|
Valley Gardens:Phase 3 – engagement and preliminary design**** |
200 |
600 |
400 |
|
Church Road, Hove |
0 |
tbc |
tbc |
|
Bus Network Review* |
30 |
tbc |
tbc |
SUB-TOTAL |
1037 |
|
|
|
Connecting people and neighbourhoods with, and improving the .............. |
||||
City Centre & Seafront |
‘Gateway to the Sea’ – engagement and preliminary design |
150 |
tbc |
tbc |
|
SUB-TOTAL |
150 |
|
|
General allocations |
||||
‘Section 106’ works |
Various agreed local measures+ |
50 |
50 |
50 |
Minor works |
Scheme completion & scoping/Monitoring |
20 |
tbc |
tbc |
|
SUB-TOTAL |
70 |
|
|
INTEGRATED TRANSPORT SUB-TOTAL |
2,032 |
3,059 |
3,059 |
|
|
|
|
|
|
TOTAL LTP ALLOCATIONS |
5,477 |
5,169 |
5,169 |
|
Funded From |
|
|
|
|
LTP Integrated Transport Block Grant Allocation |
3,059 |
3,059 |
3,059 |
|
LTP Maintenance Block Grant Allocation |
2,110 |
2,110 |
2,110 |
|
Highway Maintenance Incentive Fund |
196 |
tbc |
tbc |
|
Pothole Action Fund |
tbc |
tbc |
tbc |
|
Additional Funding Sources |
|
|
|
|
Capital Receipts – Shelter Hall and Hove Station Footbridge |
1,500 |
0 |
0 |
|
Unsupported Borrowing – Shelter Hall and street lighting |
3,805 |
3,805 |
0 |
|
Funding from/(to) Reserves – Shelter Hall |
0 |
1,000 |
-1,000 |
|
Council Direct Revenue – street lighting |
145 |
145 |
0 |
|
Local Growth Fund [LGF] – Valley Gardens Phases 1&2 and 3 |
3,573 |
6,540 |
3,000 |
|
GRAND TOTALS |
14,388 |
16,659 |
7,169 |
Footnotes
#- includes Incentive Funding indicative allocation (£196,000) and Pothole Action Fund allocation (to be confirmed)
@ - committed contribution to ‘Invest to Save’ project (PR&G Committee – 8/2/16).
* - supplemented with additional funding from various council sources (Council-22/2/18)
** - local contribution, committed to approved C2C LEP Local Growth Fund [LGF] scheme.
*** - committed contribution to successful bid to the DfT-funded ‘Unlocking Growth with Active Travel’ Access Fund project.
**** - local contribution, committed subject to acceptance of Business Case by C2C LEP to secure Local Growth Fund [LGF] allocation.
~ - supplemented with additional funding from other sources.
+- to enable design and delivery of agreed works associated with approved development.
tbc - project/programme will require/receive continued funding to deliver existing/ongoing commitments (sums to be confirmed, or unknown).
NOTES–
· In many cases, costs indicated above are preliminary estimates.
· Expenditure on schemes may need to be increased, reduced or deferred during a financial year as information becomes available, such as survey results, tender returns or unforeseen engineering difficulties.
· Some works are also subject to network co-ordination with other projects, developers and utility companies, contractor availability and weather conditions.